Production operations

This is the shop floor's daily work list: every operation of released and in-production orders that has not received its final confirmation is a row. The supervisor filters by their own work center, sees the next job and enters a confirmation from the row.

Screen
Module
Manufacturing
Menu path
Üretim › Üretim Yürütme › Üretim Operasyonları (Production › Production Execution › Production Operations)
Screen route
/erp/manufacturing/operations
Required permission
erp-manufacturing-orders.view (liste)
erp-manufacturing-postings.create (Teyit Gir)
Production Operations — work list
  1. 1Work center filter
  2. 2Only my work centers
  3. 3Remaining quantity
  4. 4Enter Confirmation — opens for this operation

Columns​

ColumnMeaning
Üretim emri (Production order)The order number (link to the order details).
Operasyon (Operation)Operation number and description (from the routing: 10 Sac ve boru kesim (sheet and tube cutting), 20 Büküm (bending)…).
İş merkezi (Work center)The operation's work center.
Tezgâh (Machine)The planned individual capacity (machine); blank if no machines are defined for the work center.
Planlanan (Planned)The planned quantity of the operation (the order quantity).
Sağlam / fire (Good / scrap)Good and scrap quantities confirmed so far.
Kalan (Remaining)Planned − (good + scrap).
Durum (Status)Başlamadı (Not started), Kısmi teyit (Partially confirmed) or Son teyit (Final confirmation).

Teyit Gir (Enter Confirmation) on the row opens the Enter Operation Confirmation form with the order and operation preselected. An operation that receives its final confirmation drops off the list.

Filters​

  • Ara (Search) — order number, product or operation text.
  • İş Merkezi (Work Center) — in work center hierarchy order; selecting a parent work center also brings its child work centers. When the work center changes, the machine filter is reset.
  • Tezgâh (Machine) — visible only in a setup with machines defined.
  • Başlangıç · Bitiş (Start · End) — the period that overlaps the operation's planned dates.
  • Sorumlu olduğum iş merkezleri (Work centers I am responsible for) — only jobs of the work centers you are responsible for.
note

The plan, confirmation totals, remaining quantity and status come from the server; the screen does not calculate them. The operation's planned dates come from Tarihleri Planla (Schedule Dates), capacity planning or finite scheduling.