Material requirements
Malzeme İhtiyaçları (Material Requirements) summarizes the current situation of each item in a single row: how much demand there is, how much is on hand and in transit, how much is short, and how much should be ordered according to the item's ordering rule. Unlike MRP, it has no time axis and does not write documents; to cover a shortage it opens the requisition or production order form with the item's code.
Screen/erp/demand/material-requirementserp-demand-material-requirements.view (görme)erp-procurement-requisitions.create (Satınalma Talebi Aç) · erp-manufacturing-orders.create (Üretim Emri Aç)| Material Requirements | MRP Koşusu (MRP Run) | |
|---|---|---|
| Time | None — current position | Day by day |
| Forecast (planned independent requirement) | Not counted | Counted |
| BOM explosion | None | Yes (dependent requirement) |
| Document | Does not write; opens the form | The run writes requisitions and planned orders |
By Item
- 1By item / By warehouse
- 2Only items with a shortage
- 3Shortage = demand − (on hand + in transit)
- 4Proposal — when below minimum
- 5Availability — if ordered today
The list is a calculation at most 1 minute old; Listeyi yenile (Refresh list) recalculates it.
| Column | Meaning |
|---|---|
| Malzeme (Material) | The item. For a discontinued item, "Kesildi → HALEF" (Discontinued → SUCCESSOR) or "Kesildi — halef yok" (Discontinued — no successor) and the quantity transferred. |
| Talep (Demand) | Production requirements + sales order balance; the sources are in the Talep (Demand) table of the details. |
| Eldeki (On Hand) | Stock; allocated quantity is not counted. |
| Yoldaki (In Transit) | Open purchasing + open production output. |
| Açık (Shortage) | Demand − (on hand + in transit). |
| Öneri (Proposal) | If the stock position is below the minimum, the quantity that brings it up to the maximum (to the minimum if there is no maximum). |
| Sipariş (Order) | The proposal or shortage rounded with the item's ordering rule (minimum order, multiple). |
| Temin (Availability) | The availability date if ordered today (today + lead time). |
| Birim (Unit) | The item's base unit. If there is a document whose unit cannot be converted, a warning: the totals are incomplete. |
Filters: Ara (Search), Yalnız açığı olanlar (Only with shortage; hides those with zero shortage), Minimumun altındakiler (Below minimum; only those with an order proposal), Benim ürünlerim (My products; I am the MRP controller). If there are no items to calculate, the screen shows "Açık belge ve stok seviyesi tanımlı kart yok — hesaplanacak bir ihtiyaç bulunmuyor." (No items with open documents or defined stock levels — there are no requirements to calculate.)
Product Requirement Details
- 1Stock position = on hand + in transit − demand
- 2Order quantity — by the item order rule
- 3Open Requisition — opens the form with the quantity
- 4Warehouse breakdown
Clicking a row opens the details:
- Talep · Eldeki · Yoldaki · Açık (Demand · On Hand · In Transit · Shortage) tiles (the allocated quantity is shown separately).
- Stok pozisyonu (Stock position; on hand + in transit − demand), Minimum / Maksimum (Minimum / Maximum), Min–maks önerisi (Min–max proposal; "Pozisyon minimumun altında — maksimuma tamamlar" — The position is below the minimum — tops up to the maximum).
- Sipariş miktarı (Order quantity), Minimum sipariş / katsayı (Minimum order / multiple), Tedarik süresi (Lead time), Temin tarihi (Availability date).
- Eksiği Kapat (Cover Shortage; if there is a shortage) or Stoğu Tamamla (Top Up Stock; only if there is a min–max proposal): Satınalma Talebi Aç (Open Purchase Requisition) for a purchasable item, Üretim Emri Aç (Open Production Order) for a producible item. The button opens the form with the item's code and the proposed quantity; the document is not created here, and you set the quantity on the form. If the item is flagged as neither purchasable nor producible, the screen shows "Kart ne satın alınabilir ne üretilebilir işaretli; önce kartın kullanım alanları düzeltilmeli." (The item is flagged as neither purchasable nor producible; correct the item's usage settings first.)
- Depo Kırılımı (Warehouse Breakdown): Depo (Warehouse) · Eldeki (On Hand) · Tahsisli (Allocated) · Serbest (Unrestricted) · Min / Maks · Öneri (Proposal) · Lokasyon (Storage Location). If no warehouse minimum is defined, "Planlanmıyor" (Not planned). If other warehouses have enough unrestricted stock, a transfer proposal note.
- Talep (Demand) and Arz (Supply) source tables: Kaynak (Source) · Belge (Document) · Karşı taraf (Counterparty) · Miktar (Quantity) · Tarih (Date).
By Warehouse
The Depo Bazında (By Warehouse) tab compares the unrestricted stock (on hand − allocated) of each product × warehouse with the warehouse minimum: Malzeme (Material) · Depo (Warehouse) · Serbest (Unrestricted) · Min / Maks · Öneri (Proposal) · Transfer (incoming / outgoing) · Öteki Depolarda (In Other Warehouses) · Lokasyon (Storage Location) · Birim (Unit). Filters Tesis (Plant), Depo (Warehouse) and Minimumun altındakiler (Below minimum). The warehouse minimum is defined in Depo Verileri (Warehouse Data) in the Stock view of the product details; if none is defined, the list says "Depo minimumu tanımlı ürün yok …" (No products with a defined warehouse minimum …).