Dispatch an operation to capacity

Task
Module
Manufacturing
Menu path
Üretim › Kapasite Planlama › Kapasite Planlama Tablosu (Production › Capacity Planning › Capacity Planning Table)
Screen route
/erp/manufacturing/capacity/planning-table
Required permission
erp-manufacturing-capacity.view
erp-manufacturing-capacity.edit
Prerequisites
  • The operation belongs to a released or in-production production order and has not received its final confirmation (the operation of a draft order is created on release).
  • The work center's capacity is defined (if not, an 8-hour weekday is assumed).

Capacity Load only displays; to balance (level) the load, operations are moved one by one to another day in the Capacity Planning Table. To sequence all open operations at once, use the Finite Scheduling proposal.

Steps​

  1. On the Üretim › Kapasite Planlama › Kapasite Yükü (Production › Capacity Planning › Capacity Load) screen, find the overloaded work center; open the table from its row or from the Planlama Tablosu (Planning Table) link in the header.
    Open screen/erp/manufacturing/capacity
    Capacity Load — work center × week
    1. 1Bucket — Day or Week
    2. 2Include planned orders load
    3. 3Only work centers I am responsible for
    4. 4Required / available hours and utilization %
  2. Select the work center in the İş merkezi (Work center) field; if necessary, change the window with Başlangıç (Start) and Bitiş (End).
    Selectİş merkeziValue: BOYA · Elektrostatik BoyahaneExpected: The operations in the window and the total load
  3. Click Yerleştir (Dispatch) on the production order row you want to move.
    ClickYerleştirExpected: The Operasyonu Yerleştir — UE-… · 30 (Dispatch Operation) window
  4. Select the Başlangıç günü (Start day); for a work center with workstations, optionally select a Tezgâh (Workstation).
    EnterBaşlangıç günüValue: 05.11.2026
    Dispatch Operation dialog
    1. 1Start day
    2. 2Dispatch
  5. Click Yerleştir (Dispatch) in the window.
    ClickYerleştirExpected: The notification "UE-… · operasyon 30 yerleştirildi." (UE-… · operation 30 dispatched.); the row shows the Elle yerleştirildi (Manually dispatched) mark and the new dates
    Capacity Planning Table — manually dispatched operation
    1. 1Select a work center
    2. 2Manually dispatched marker
    3. 3Dispatch — choose the start day
    4. 4Remove — back to base date
Result
The operation starts on the selected day; its end is calculated from the work center's capacity. The subsequent operations of the same order that were not dispatched manually shift accordingly. To undo the dispatch, click Kaldır (Remove) → Kaldır on the row: the operation is rescheduled from the order's basic dates.

What you need to know​

  • Only production order operations are dispatched; planned order rows (when Planlı emirler dâhil (Include planned orders) is on) only show the load.
  • A manually dispatched operation stays in place in the next automatic scheduling; the finite scheduling proposal also leaves it in place with a grey bar.
  • A restricted user can dispatch only the operations of the work centers they are authorized for.
  • Demo example: operation 30 "Toz boya" (Powder coating) of order UE-2026-000007 was dispatched to 05.11.2026 at the BOYA work center.