Run MRP
Module
Manufacturing
Menu path
Üretim › Üretim Planlama › MRP Koşusu (Production › Production Planning › MRP Run)
Screen route
/erp/demand/mrpRequired permission
erp-demand-material-requirements.viewerp-demand-mrp-runs.createPrerequisites
- The Planlama stratejisi (Planning strategy) of the cards to be planned is *Stoğa Üretim* (Make-to-Stock) or *Siparişe Üretim* (Make-to-Order), and the Varsayılan tedarik yolu (Default procurement type) is filled in (Planlama Verileri (Planning Data)).
- For safety stock, Minimum stok (Minimum stock) is defined on the card, and for the proposal ceiling Maksimum stok (Maximum stock) (Stok Verileri (Stock Data); optional).
- The produced card has a released bill of materials — otherwise the proposal cannot be exploded.
The run converts the proposals you see in the list into documents. The list itself is always a simulation; the run writes only with MRP'yi Çalıştır (Run MRP) or with the nightly job.
Steps
- Open the Üretim › Üretim Planlama › MRP Koşusu (Production › Production Planning › MRP Run) screen. The list is recalculated every time it is opened; nothing is written yet.
MRP Run — planned products, proposals and exceptions - 1Run MRP — writes requisition and planned orders
- 2Simulation — scenario, writes nothing
- 3Nightly job — automatic run every night
- 4Only items with proposals
- 5Proposed quantity and its outcome (requisition / planned order)
- 6Exception badges — hover for the message
- Turn on the Yalnız önerisi olanlar (Only items with proposals) switch and review the proposals. To see the reasoning for a card, click its row; the Stok/İhtiyaç Listesi (Stock/Requirements List) shows supply, requirements and proposals day by day.
Stock/Requirements List — item timeline - 1Safety stock = item minimum; proposal fills up to the maximum
- 2Proposals — requirement, start, delivery
- 3Timeline — available quantity element by element
- 4Pegging — where the requirement comes from
- Check the badges in the İstisnalar (Exceptions) column (e.g. Tedarik süresi yok (No lead time), Ağaç yok ya da uygun alternatif/geçerli revizyon yok (No BOM or no suitable alternative/valid revision)) and correct the card's planning data if necessary.
- To try a scenario, optionally open Simülasyon (Simulation): enter a Tahmin ölçeği (%) (Forecast scale, %) and additional demand and press Simüle Et (Simulate). The simulation does not write anything.
MRP Simulation — forecast scale and extra demand - 1Forecast scale — 100 as is
- 2Extra demands — item, date, quantity
- 3Simulate — writes nothing
- 4Items whose proposal changes (current → scenario)
- Click MRP'yi Çalıştır (Run MRP).
Run MRP confirmation - 1Unfirmed MRP orders are rebuilt
- 2Make to order: order pegged to sales item
- 3Run
- Click Çalıştır (Run) in the window.
- Go to the planned orders with the Planlı Emirler (Planned Orders) link in the result, and to the draft requisition with the requisition number. If there is a Talebe ya da planlı emre giremeyen öneriler (Proposals that could not be included in a requisition or planned order) list, resolve the causes.
Result
The proposals for purchased cards are written to a single draft purchase requisition (TLP-yyyy-nnnnnn), and the proposals for produced cards to planned orders (PLO-yyyy-nnnnnn). The requisition remains a draft until you send it. Next step: convert the planned order into a production order.
What you need to know
- Running again is safe: an old MRP draft requisition that has not been sent or edited, and MRP planned orders that have not been firmed, are cancelled and rebuilt. A requisition that has been sent or edited, and a planned order that has been firmed, changed or opened manually, are kept and count as supply. The cancelled documents are listed with their numbers in the result section.
- If you want to keep a planned order, firm it or convert it into a production order before the run.
- The window carries a single key against double clicks: a second run from the same window does not open a second requisition.
- The proposal for a make-to-order card is generated per sales order item, and the planned order is linked to that item; the configuration comes from the sales order item.
- It is normal for proposals to still appear in the list after the run: a planned order from MRP that has not been firmed does not count as supply.
- If an error occurs, the window shows "MRP koşusu tamamlanamadı." (The MRP run could not be completed.) and the server's reason; the window stays open and you can try again.