# Create a production order

> Open a draft production order from a released BOM revision — plan source, planned quantity and work center.

URL: https://erpdocs.corexlogic.com/en/uretim/islemler/uretim-emri-olusturma

- **Type:** Task
- **Module:** Manufacturing
- **Menu path:** Üretim › Üretim Yürütme › Üretim Emri Oluştur (Production › Production Execution › Create Production Order)
- **Screen route:** `/erp/manufacturing/orders/new`
- **Required permission:** `erp-manufacturing-orders.create`
- **Prerequisites:**
  - The **Üretilir** (Produced) flag of the card to be produced is on, the card is active and it is not a service card.
  - The card has a **released** BOM revision with production usage whose validity has started.
  - For a configurable item, the order is opened from a sales order — [Open a production order from a sales order](https://erpdocs.corexlogic.com/en/uretim/islemler/siparisten-uretim-emri-acma).

A production order states with which BOM revision and in what quantity an item is to be produced. The order is opened
as a **draft**; in draft, the quantity, revision and work center can be edited.

## Steps

1. Open the **Üretim › Üretim Yürütme › Üretim Emri Oluştur** (Production › Production Execution › Create Production Order) screen. If you are in the list, click **Yeni Üretim Emri** (New Production Order).
   <!-- action: navigate · target: "/erp/manufacturing/orders/new" · expect: "The Yeni Üretim Emri (New Production Order) form; Plan Kaynağı (Plan Source) on the left, Planlanan Miktar (Planned Quantity) on the right" -->
2. Type the code or name of the output card in the **Ürün ağacı ara** (Search BOM) box; select the BOM (with its alternative and revision) from the list.
   <!-- action: fill · target: "Ürün ağacı ara" · value: "MAM-0010" · expect: "The card is marked as selected; Çıktı Kartı (Output Card) and Revizyon (Revision) are shown on the right" -->
3. Click the **PASLANMAZ ÇALIŞMA TEZGAHI 150X70 · Rev 1** card in the list.
   <!-- action: click · target: "PASLANMAZ ÇALIŞMA TEZGAHI 150X70" -->
4. Enter the **Planlanan Miktar** (Planned Quantity) in the output unit. The unit comes from the revision and cannot be changed; the decimal limit is shown under the field.
   <!-- action: fill · target: "Planlanan Miktar" · value: "2" -->
5. If you wish, select the **İş Merkezi** (Work Center) (the station for which the order is planned; where the work is actually done is recorded separately on consumption and output).
   <!-- action: select · target: "İş Merkezi" -->
6. Click **Üretim Emrini Kaydet** (Save Production Order).
   <!-- action: click · target: "Üretim Emrini Kaydet" · expect: "The order detail opens; number UE-yyyy-nnnnnn, status Taslak (Draft)" -->

   ![New Production Order — BOM and quantity chosen](https://erpdocs.corexlogic.com/en/en/img/screens/uretim/emir-olustur.png)
   1. Search BOM — released revisions only
   2. Plan source: BOM and revision
   3. Planned Quantity — unit from the revision
   4. Work center — optional
   5. Save — order is created as Draft

**Result:** The order is saved with the number **UE-yyyy-nnnnnn** in **Taslak** (Draft) status. There is no stock movement or material reservation; the requirements are created on release. Next step: [Release the production order](https://erpdocs.corexlogic.com/en/uretim/islemler/uretim-emrini-yayinlama).

## What you need to know

- The list shows only the released revisions, whose validity has started, of BOMs with **production** usage; older
  released revisions can also be selected. If the card has several alternatives, the lot-size range is shown next to
  them. No order can be opened from an engineering BOM.
- If the quantity produces a fraction in a piece-based component, the order cannot be released (no silent rounding).
  Example: the BOM of MAM-0008 has 25 cartons for 100 ADET (pcs); 50 ADET makes 12.5 cartons, and on release the
  message "… 'ADET' biriminin 0 ondalık basamak sınırını aşıyor" (… exceeds the 0 decimal place limit of the 'ADET'
  unit) appears. Set the quantity to a suitable multiple of the BOM's base quantity.
- For a serial-managed output, the planned quantity must be an integer.
- In draft, **Düzenle** (Edit: quantity, revision, work center), **Böl** (Split), **Tarihleri Planla** (Schedule Dates),
  **Malzeme Talebi** (Material Requisition) and **İptal Et** (Cancel) are available. When you leave an unsaved form, the
  system asks you.
- **Ağaçsız Emir** (Order without BOM) (the button in the list): an order for a card without a BOM in which you enter
  the components manually. The component list can be left empty, but an empty order cannot be released; when the
  quantity changes, the components are not scaled.
- If you are coming from planning, the order is converted from a planned order: [Convert a planned order](https://erpdocs.corexlogic.com/en/uretim/islemler/planli-emri-donusturme).

### Common messages

| Message | English meaning | Cause |
|---|---|---|
| Planlanan miktar zorunlu. | The planned quantity is required. | The quantity is empty (form validation). |
| Planlanan üretim miktarı sıfırdan büyük olmalıdır. | The planned production quantity must be greater than zero. | The quantity is 0 or negative. |
| 'KART' üretilen kart olarak işaretlenmemiş — üretim emri açılamaz. Kartın 'Üretilir' bayrağını açın. | 'KART' is not flagged as a produced card — a production order cannot be opened. Turn on the card's 'Üretilir' flag. | Üretilir (Produced) is off on the card. |
| 'KART' pasif — pasif stok kartı için üretim emri açılamaz. | 'KART' is inactive — a production order cannot be opened for an inactive stock card. | The card is inactive. |
| Mühendislik ağacından üretim emri açılamaz — üretim kullanımındaki bir ağaç seçin. | A production order cannot be opened from an engineering BOM — select a BOM with production usage. | Wrong usage. |
| Üretim emri yalnız yayınlanmış ürün ağacı revizyonu üzerinden oluşturulabilir. | A production order can be created only from a released BOM revision. | The revision is a draft. |
| Revizyon \{n\} \{tarih\} tarihinden itibaren geçerli — bugün emre verilemez. | Revision \{n\} is valid from \{tarih\} — it cannot be used for an order today. | Validity is in the future. |
| 'MAM-0001' yapılandırılabilir kart — üretim emri yalnız yapılandırılmış bir satış siparişi satırından açılır. | 'MAM-0001' is a configurable card — a production order can be opened only from a configured sales order line. | A configurable item was selected manually; open the order from the sales order. |

## Related

- [Production orders screen](https://erpdocs.corexlogic.com/en/uretim/ekranlar/uretim-emirleri)
- [Release the production order](https://erpdocs.corexlogic.com/en/uretim/islemler/uretim-emrini-yayinlama)
- [Make-to-stock process](https://erpdocs.corexlogic.com/en/surecler/stoga-uretim)